Fulvio Roman Direttore Project Management LA GESTIONE DELLE COMMESSE IMPIANTISTICHE CHIAVI IN MANO & C. Officine Meccaniche S.p.a.

Presentazioni simili


Presentazione sul tema: "Fulvio Roman Direttore Project Management LA GESTIONE DELLE COMMESSE IMPIANTISTICHE CHIAVI IN MANO & C. Officine Meccaniche S.p.a."— Transcript della presentazione:

1 Fulvio Roman Direttore Project Management LA GESTIONE DELLE COMMESSE IMPIANTISTICHE CHIAVI IN MANO & C. Officine Meccaniche S.p.a.

2 DANIELI THE RELIABLE INNOVATIVE TEAM IN THE METALS INDUSTRY

3 Product lines

4

5 Worldwide companies and offices Danieli Companies France Germany Spain Sweden Danieli Offices Brazil Canada China Egypt United Kingdom USA The Netherlands Russia India Korea Malaysia Mexico Taiwan Thailand Danieli Headquarters Italy

6 Danieli Scorecard 97 Complete turnkey plants, designed, engineered, manufactured, erected and commissioned worldwide since 1967

7 Gestione di una commessa Turn-Key Premessa Cosa è un contratto Cosa è un Turn-Key Project

8 Gestione di una commessa Turn-Key 4.1 Basic Design 4.2 Detail Engineering 4.3 Procurement 4.4 Manufacturing 4.5 Workshop testing e Pre-shipment inspections 4.6 Shipment, Custom clearance and site forwarding 4.7 Construction and erection 4.8 Commissioning, Performance demonstration e Provisional Acceptance 4.9 Guarantee period e Final acceptance Fasi principali di un Turn-Key Project 4

9 Gestione di una commessa Turn-Key > Uffici tecnici macchine e processo > Uffici tecnici sistemi ausiliari > Uffici tecnici opere civili / infrastrutture > Uffici tecnici sistemi fluidi > Uffici tecnici sistemi elettrici e automazione > Uffici gestione construction, erection e commissioning > Ufficio Acquisti > Produzione > Expediting, collaudi, ispezioni > Spedizioni > Project Management, Project Planning, Control & Administration > Uffici finanziari e legali Interfacce interne commessa Chiave in mano 5

10 Gestione di una commessa Turn-Key > Organizzazione Clienti > Consulenti dei Clienti (Engineers) > Organizzazione di cantiere per construction, erection e commissioning > Enti Certificatori indipendenti > Sub-fornitori di sistemi, materiali, componenti e servizi > Uffici tecnici esterni > Sub-contrattisti opere civili e montaggi > Partners consortili / Joint Ventures > Enti finanziatori / Banche > Assicurazioni Interfacce esterne commessa Chiave in mano 6

11 Turn-key Project Key-Personnel Organisation chart Safety Officier Planning & quantity Survey Quality Assurance Eng. Accounting & Cost control Building erection Mechanical equipment Reheating furnace Piping and aux. Systems HV / LV power distribution & Automation system Mechanical Electrical Piping Director, Projects Sales Manager Export Finance & L/C Manager Legal Dept. Manager Procurement Manager Quality Manager Client Project Manager & Project Management Staff P.M. DMH P.E. Rolling process P.E. Mech. Equipment eng. P.E. Hydraulics Lubrication P.E. Piping Utilities P.E. Instrumentation P.M. DCC P.E. Combustion process P.E. L.V. Distribution P.E. Automation P.M. DE P.C. WTP process P.E. Civil & structural des. P.E. Interconnecting piping P.E. Instrumentation P.E. HVAC P.E. Firefighting system P.E. Compressed air system P.C. Workshop laboratory eq. P.C. Cranes P.M. DA Process Coordinator P.E. Substation, HV - LV power distrib. P.E. Interconnecting cabling P.C. Automation system level 1 P.C. Automation system level 2 P.M. DCM P.E. Meltshop process P.E. Mech. Equipment engin. P.E. Hydraulics lubrication P.E. Piping utilities P.E. Instrumentation Site Technical Office Field Engineers Civil and infrastructure construction Supervisor Erection SupervisorsStartup and commissioning Team Material Man Client Site manager & Staff P.C. Spare partsP.C. Packing & Shipping P.C. TrainingP.C. Operation, maintenance & safety manuals P.C. Expediting / testing (E LE) P.C. Quality Control P.C. Manufacturing & expediting P.C. Procurement cc Danieli Construction & Commissioning (UMAC) P.M. Construct Erection & Commiss. Site Manager Deputy Site Manager Danieli Engineering (DE) Project Manager Project Planning & Control Contract Administr. Automation Aux. Systems

12 General Management Flow Chart (part 1) SCHEDULE (LEV. III) WORK BREAKDOWN PRICE BREAKDOWN JOB POSITION (TPC/JET) INSPECTION TEST SCHEDULE (ITS) CASH FLOW (PART 2)(PART 3) RESPONSIBILITY CONTRACT & FINANCING TOOLS REQUIREMENTS MASTER PLANT LIST TECHNICAL SPECIFICATIONCONTRACT SCHEDULEPAYMENT METHOD/FORMALITIES PICS (PROJECT INTEGRATED CONTROL SYSTEM)

13 General Management Flow Chart (part 2) OUTSIDE (E/LE)INSIDE (I) (PART 3) ENGINEERING (DOCUMENT MANAGEMENT SYSTEM - DMS) TECHN. DOCUMENTS JOB POSITION (TPC / JET) from part 1 MATERIAL REQUIR. PROCUREMENT PURCHASE & ORDERS MANUFACTURING

14 General Management Flow Chart (part 3) INSPECTION & TESTING (NOI/IRE/LOC/QCTM) OUTSIDE (E)INSIDE (I/LE) INSPECTION TEST SCHEDULE (ITS) (FROM PART 1) CERTIFICATIONS (IRE) SHIPPING & INVOICING CERTIFICATION (IRP) PACKING LIST INSPECTION PLANNING NOTICE OF SURVEILLANCE (NOS) PACKING COMMISSIONING JOB POSITION (TPC/JET) (FROM PART 1) RELEASE CERTIFICATE (RC) PRICE BREAKDOWN (FROM PART 1) MANUFACTURING (FROM PART 2) INSPECTION PLANNING NOTICE OF INSPECTION (NOI) CONSTRUCTION & ERECTION WORKS SITE PROGRESS MANAGEMENT (SPM)

15 Master Plant List (example)

16 Estratto Livello 3: Plant Unit 31 (Typical)

17 Programmazione di Livello 3 (Typical)

18 Programmazione di Livello 4 (Typical)

19 Cut-off date: Progress (Typical)

20 Curve pianificate di avanzamento (Typical) planned progress % NDJMFAMJJASONDJMFAMJJASONDJMFA Valide per tutte le discipline e attività

21 Esempi di fasi di avanzamento lavori (parte 1) Inizio disegno:10% Prima stesura disegno:20% Disegno commentato :30% Disegno approvato interno:30% Disegno approvato da Cliente:10% ESEMPIO DI FASI DI MANUFACTURING DI UNA MACCHINA Approvvigionamento grezzi:10% Disponibilità grezzi:10% Costruzione carpenteria:10% Costruzione parti meccaniche:10% Machining: 20% Assemblaggio sottogruppi: 10% Assemblaggio macchina: 15% Collaudo:3% Protezioni superfici: 10% Approntamento per la spedizione:2% ESEMPIO DI FASI DI ESECUZIONE DI UN DISEGNO

22 ESEMPIO DI FASI DI ESECUZIONE DI UNA FONDAZIONE Scavo: 5% Getto magrone: 2% Casseforme:28% Ferri di armatura:35% Getto cementi:25% Disarmo e finitura/curing:5% ESEMPIO DI FASI DI ESECUZIONE MONTAGGIO TUBAZIONI Movimentazione:5% Assiemaggio a terra:25% Montaggio supporteria:15% Montaggio e saldatura linee:35% Controlli non distruttivi:5% Decappaggio e flussaggio:10% Collaudi:5% Esempi di fasi di avanzamento lavori (parte 2)

23 Gestione di una commessa Turn-Key > M.P.L. (Master Plant List) > D.M.S. (Documentation Management System) > Procurement & Manufacturing Progress > Pre-shipment inspection > Shipment > Invoicing > Cash-flow > Construction & erection > Commissioning & Performance test Funzionalità e strumenti del P.I.C.S.

24 Gestione di una commessa Turn-Key Project Manager