Stato esperimento JUNO e JUNO Italia Gioacchino Ranucci INFN - Milano Commissione II Sestri Levante, 22/9/2015 Obiettivi raggiunti dalla Collaborazione nell’ultimo anno Scansione delle scelte progettuali nell’immediato futuro Articolazione di JUNO Italia
Lo scavo del sito sperimentale è iniziato
Updated list of members Beijing, July 20153M. Dracos CountryInstitute ArmeniaYerevan Physics Institute BelgiumUniversite libre de Bruxelles ChilePCUC ChinaBeijing Normal U. ChinaCAGS ChinaChongQing University ChinaCIAE ChinaDGUT ChinaECUST ChinaGuangxi U. ChinaHarbin Institute of Technology ChinaIHEP ChinaJilin U. ChinaNanjing U. ChinaNankai U. ChinaNCEPU ChinaPekin U. ChinaShandong U. ChinaShanghai JT U. ChinaSichuan U. ChinaSYSU ChinaTsinghua U. ChinaUCAS ChinaUSTC ChinaWu Yi U. ChinaWuhan U. ChinaXi'an JT U. ChinaXiamen University CzechCharles U. FinlandUniversity of Oulu FranceAPC Paris FranceCPPM Marseille FranceIPHC Strasbourg FranceLLR Paris FranceSubatech Nantes GermanyForschungszentrum Julich GermanyRWTH Aachen U. GermanyTUM GermanyU. Hamburg GermanyU. Mainz GermanyU. Tuebingen ItalyINFN di Frascati ItalyINFN-Ferrara ItalyINFN-Milano ItalyINFN-Milano Bicocca ItalyINFN-Padova ItalyINFN-Perugia ItalyINFN-Roma 3 RussiaINR Moscow RussiaJINR TaiwanNational Chiao-Tung U. TaiwanNational Taiwan U. TaiwanNational United U. USAUMD1 USAUMD2 USABNL USAHouston USAUIUC USA… waiting for DoE/NSF decision =55 groups Actually negative decision… discussions in progress with Fermilab management for some form of CHINA-US reciprocity
Updated list of observers Beijing, July 20154M. Dracos 1.Department of Physics, Jyvaskyla University, (Finland): Wladyslaw Henryk Trzaska 2.HEPHY Vienna (Austria): Manfred Jeitler 3.PUC (Pontificia Universidade Catolica do Rio de Janeiro, Brazil): Nunokawa Hiroshi 4.Universidade Federal do ABC (Sao Paulo, Brazil): Pietro Chimenti 5.Moscow State University (Russia)
In particolare per JUNO – Italia Application di Milano Bicocca a Maggio all’IB e membership approvata ufficialmente a Luglio Ingresso in JUNO Italia di Catania a Giugno Formalizzazione della candidatura all’IB entro l’autunno per discussione e approvazione nella riunione di Collaborazione di Gennaio In totale 8 sezioni nei preventivi
Prima importante traguardo del progetto: avvio dello scavo Iniziato a fine 2014 Cerimonia ufficiale di inaugurazione Gennaio 2015 Prevista fine dei lavori del sito Dicembre 2017
Jan. 10, m vertical shaft 1300-m long tunnel(40% slope) 50-m diameter, 80-m high cavern
9
Secondo traguardo: pubblicazione dello Yellow book Arxiv:
Terzo traguardo: pubblicazione del CDR Arxiv: Logo ufficiale scelto a gennaio
Decisioni dopo le Review durante l’ultimo Collaboration meeting Sistema PMT da 3” : sì o no ? – Adeguati per calibrazioni, cosmici & supernovae – Costo per 35K PMT: ~ 12 M Euro, da ottimizzare ? Central Detector: pallone o acrilico ? – Entrambe le opzioni funzionanti Decisioni dell’ EB+TB, a seguito delle raccomandazioni dei review committee: 3” PMT Approvati a condizione della disponibilità di risorse – quarto traguardo Per il contenitore dello scintillatore si è deciso per l’acrilico - quinto traguardo
Sesto traguardo: definizione della schedula complessiva Confermato avvio della presa dati per il 2020
Startendcondition 1Underground lab construction Water pool cleaning and CD construction preparation CD & water poll equipment installation PMT base(& to be sealed electronics) design finalized PMT base production and aging test PMT bidding PMT mass production PMT testing PMT potting and testing CD & VETO PMT installation Readout electronics design finalized Readout electronics mass production Readout electronics testing and aging Readout electronics installation CD & water pool cleaning Water pool cover is placed TTS supporting structure installation TTS installation AD & VETO water filling LS filling Test run
Decisioni di progetto per il breve termine Elettronica Review esaustiva degli schemi alternativi proposti già effettuata al meeting di Luglio Decisione definitiva a Ottobre nella riunione specifica che si terrà a Padova Entro Novembre Review sistema di test della purificazione a Daya Bay Progetto della zona del camino del vessel (zona cruciale di interfaccia di diversi sistemi)
Altre review nell’immediato futuro Preliminary Design Review previste al meeting di Collaborazione di Gennaio: – VETO – LS Onsite facility – Slow control – PMT testing, potting, protection, HV, base, … – Integration
Tappa fondamentale del progetto scelta del tipo di fototubo Procedura da espletare tra Novembre e Dicembre Ditte invitate Hamamatsu North Vision Hainan ZhanChuang (former Photonis) Selection committee da istituire in Ottobre
Project Management Team Project manager: Y.F. Wang Deputy manager: J. Cao , G. Ranucci Chief engineer: H.L. Zhuang , XXX Chief technical support : XXX Safety officer: XXX L2 System manager : – Civil : X.N. Li – CD : Y.K. Heng , Y. Hsiung – VETO : M. Dracos , C.G. Yang – LS : L. Zhou , G. Rannucci – MCP-PMT: S.L. Liu – PMT(testing, potting, shielding, base, assembly, HV…): W. Wang, Z.H. Qin, A. Olshevskiy – Electronics & Trigger &HV : X.S. Jiang , A. Stahl – Calibration: J.L. Liu, – Integration: H.L. Zhuang – DAQ & Slow control : K.J. Zhu, …… – Offline & computing: W.D. Li , XXXX
Technical Board Managers + Chief engineers/tech. support + safety officer + One of L2 + Z. Wang, W.G. Li, P. Lombardi, L. Oberauer, A. Olshevskiy Responsibilities – Discuss all technical related issues – Examine review results – Technical recommendations to managers
Background Task Force Jie Zhao, Ezio Previtali, Jian Tang, Olivier Drapier , Task: Collect material background database Organize background measurements Collect detector requirements, establish background budget Inform everybody the bkg limits Review bgk control plans & practice of sub-systems Inspect and ensure the satisfaction of bkg control plan
I nostri contributi Partecipazione al muon veto working group (Frascati) Top tracker Partecipazione al working group sullo scintillatore (Milano, Perugia, Milano Bicocca) Progettazione impianti purificazione, quality control dei materiali costruttivi Misure di Laboratorio di caratterizzazione ottica Partecipazione al working group sull’elettronica (Padova) Progetto GCU Partecipazione alle simulazioni MC (Ferrara, Roma3, Padova, Milano)
I nostri contributi Partecipazione al computing (Roma3, Padova, Catania) Studi sul Geo-neutrino, incluso survey geologico del sito (Ferrara) Misure di bassa radioattività dei materiali (Milano Bicocca) Monitoraggio dei reattori (Milano Bicocca)
Oggetto richieste finanziarie per 2016 Partecipazione meeting generali e working group Commissioning test a Daya Bay Test e prototipazioni elettronica central detector e TT Avvio gara elettronica Test scintillatori, misure radioattività Computing (il CNAF non compare su questa preventivo) MC e geoneutrino Calcolo
JUNO-RomaTre Capitolo (keuro) Commento Missioni General Meeting, 2 Working Group meeting, 1 meeting europeo 2 meeting in italia, 1 Conferenza Consumo 1.0 metabolismo interno Inventario 1.0 rinnovo postazioni di calcolo individuale
Decisione management INFN sulla suddivisione finanziamenti Investimento capitale per il nostro contributo al sistema di purificazione complessivo di JUNO (Distillazione & Stripping) Dalla Giunta - Extra Commissione Richiesta di finanziamento specifico al MISE Gli altri item restano di pertinenza della Commissione Le missioni per le attività dello scintillatore restano in capo alla Commissione, cosi’ come il test a Daya Bay (già finanziato)
Riunione del Financial Resource Board a Parigi 27 Ottobre Per INFN Antonio Masiero e Marco Pallavicini Inizio formalizzazione suddivisione dei finanziamenti MoU
Riunioni in Europa Forte integrazione internazionale Gruppi di lavoro congiunti Round di riunioni di working group in Europa a Ottobre Scintillatore a Oulu (Finlandia) metà Ottobre Elettronica a Padova Ottobre Presumibile riunione componente europea a Marzo anno prossimo
Missioni Milano 5 keuro Attività scintillatore Missioni Frascati 2 keuro Attività top tracker Altri_consumi 10 keuro Nuove richieste per il 2015
Conclusioni L’esperimento è entrato in pieno nella fase di progettazione E’ fondamentale il mantenimento della schedula e la conseguente l’erogazione dei finanziamenti per mantenere in maniera «timely» nostri impegni
Back up slides
Roma, July 7, 2015Gioacchino Ranucci - INFN Sez. di Milano Global Funding request All figures in Keuros Liquid scintillator purification plant (specific funding) 8751 Committee II Daya Bay test (620 already given in 2015) LS Laboratory measurements Electronics central detector (60 already given in 2015) Electronics top tracker (15 already given in 2015) Computing Geoneutrinos MC Low rad meas. Reactor monitoring Total 5717 (705 already given) → about 5000 capital investement plus consumable plus computing in 4 years Moreover Missions: 1200 over the same period Temporary contracts: 939
Composizione dei vari board IB: 55 componenti Italiani 7: Barbara Ricci, Riccardo Brugnera, Fausto Ortica, Stefano Mari, Alessandro Paoloni, Ezio Previtali, Gioacchino Ranucci Chair dell’IB: Marcos Dracos Spokesperson: Yifang Wang Deputy: Jun Cao, Gioacchino Ranucci EB: Yifang Wang, Michi Wurm, Steve Kettel, Gioacchino Ranucci, Jun Cao, Changgen Yang, Yee Hsiung, Jianglai Liu, Dmitry Naumov Altri board formati: publication committee - Alberto Garfagnini - speaker committee - membership committee