GRI M. Diemoz - INFN Roma ECAL Maggio 2005
GRI M. Diemoz - INFN Roma Indice Cristalli Stato costruzione CR Integrazione Super moduli Stato impegni INFN
GRI M. Diemoz - INFN Roma Cristalli : BTCP Delivery continues according to the plan (~ 1200 xl/month). New Contract for 18K Barrel EE (on top of the in-kind contribution) in preparation with Russian Electronics Key issue is the delivery schedule. We want to be firm on the 1200 EB /month rate, which would correspond to the last EB crystal in October 06 and allow us to complete EE before the run of 2008 In-kind contribution of 7000 EE crystals (1 Endcap) from Russian federation has been confirmed in a letter from minister Fursenko to DG Aymard
GRI M. Diemoz - INFN Roma Cristalli: SIC We have completed the 300 EE pre-series A pre-series of 100 EB crystals (50 type-14 L+R and 50 type-17 L+R) is being cut and should be sent very soon Second draft of contract being exchanged Issues –Pt import/export authorization (si importa ma non è chiaro se si esporta...) –Radiation hardness specifications Non ancora trovata una correlazione utilizzabile tra parametri ottici e radiation hardness. Intensa attività di irraggiamento per capire il comportamento di questi cristalli
GRI M. Diemoz - INFN Roma Impianto Calliope-ENEA Casaccia Attività sorgente (01/05): 6.72x10 14 Bq (18.1 kCi) Responsabile: S. Baccaro Attività irraggiamenti per qualifica SIC: 100 cristalli trattati 4100 h di irraggiamento a 3 dose rates nuovo set-up per irraggiamenti multipli
GRI M. Diemoz - INFN Roma Radiation hardness SIC Radiation induced damage at 420 nm after 1h 350 Gy/h specifica BOGO Come rigettare i cattivi? SIC può pre-irraggiare i xl in una infrastruttura industriale (sterilizzazione alimentare): (????) 30 Gy/h x 24 h condizioni da verificare con appropriate dosimetrie in loco
GRI M. Diemoz - INFN Roma Radiation hardness SIC SIC EE Xtls BTCP EE Xtls (HDR_specs_CMS) (LDR_SIC_cond) Si può stabilire un criterio di reiezione all’origine provvisto che le condizioni di irraggiamento siano sotto controllo m=1.19±0.01 saturation 11.8 Gy/h (m -1 ) EE dose rate Irraggiamenti ENEA: confronto dose rates diverse
GRI M. Diemoz - INFN Roma Radiation hardness SIC (420nm) (420nm) after 1h Gy/h vs. saturation 30 Gy/h ENEA preliminare
GRI M. Diemoz - INFN Roma Radiation hardness SIC Comparison Rome & SIC after 720 Gy at 30 Gy/h PRELIMINARE = 15% Vedere una chiara correlazione è un passo avanti non trascurabile!
GRI M. Diemoz - INFN Roma Prossima milestone ECAL Installazione di EB+ in SX5 tra DIC 05- GEN 06 Milestone non soggetta alle incertezze dovute all’arrivo dei cristalli
GRI M. Diemoz - INFN Roma Stato costruzione Moduli & S-Moduli-1 SM0SM0 SM1SM1 SM2SM2 S M3 SM4SM4 SM5SM5 SM6SM6 SM7SM7 SM8SM8 SM9SM9 S M 10 S M 11 S M 12 S M 13 S M 14 S M 15 S M 16 S M 17 M1 CERN M2 Rome M3 Rome M4 CERN Bare SM Complete SM Module Completed in RC Module In progress Module Completed & shipped to CERN/lab27 Bare* Super-Module Completed Super-Module In progress
GRI M. Diemoz - INFN Roma Stato costruzione Moduli & S-Moduli-2 S M 18 S M 19 S M 20 S M 21 S M 22 S M 23 S M 24 S M 25 S M 26 S M 27 S M 28 S M 29 S M 30 S M 31 S M 32 S M 33 S M 34 S M 35 S M 36 M1 CERN M2 Rome M3 Rome M4 CERN Bare SM Complet ed SM Module Completed in RC Module In progress Module Completed & shipped to CERN/lab27 Bare* Super-Module Completed Super-Module In progress
GRI M. Diemoz - INFN Roma Un traguardo di rilievo The CERN ECAL team invites you to an aperitif to celebrate the mechanical completion of the first half Barrel Building 27, starting at 18:00, on Wednesday, April 20 th.
GRI M. Diemoz - INFN Roma Integrazione - 1 Production of SM now in a “routine” mode: since Sept 03 one SM assembled nearly every 3/4 weeks (1 week mechanical assembly, 2 weeks (7 days) monitoring installation) 17 bare SM ready to be integrated with front-end electronics & cooling Installation of rear DCS sensors (1/module), Installation of water “leak detection” cable, Installation of Armaflex Installation of 4 Inlet manifolds + He leak test Installation of 4 return pipes + He leak test Installation HV cables Installation of motherboard supports Installation Mother boards + test Installation cooling blocks (equipped with the electronic services support) +He leak test Installation of SM general manifolds + He leak test Installation DCS sensors in manifold Pressure 20bar Helium leak test Last tests on MB Water filling, hydraulics tests Install back plate Mi-bare SM integration (HV & Cooling & Motherboard):
GRI M. Diemoz - INFN Roma Integrazione Bld 867
GRI M. Diemoz - INFN Roma Integrazione - 2 Most recent advances: Staffing of three complete teams from ~July on ETHZ (+ Sofia) Minnesota, IN2P3, IC INFN Three benches ready (for TT test level), full SM test implementation will follow Quality insurance policy, with non conformity certificates, proposed by J. Nash Controlled access system ordered The recommendations from the MPR review committee (DEC 04) have been implemented
GRI M. Diemoz - INFN Roma Integrazione - 2 Crystal APD Amplifier *1 Amplifier *6 Amplifier *12 ADC Channel 2 (12bit) ADC Channel 1 (12 bit) ADC Channel 0 (12 bit) Crystal Motherboard Very Front End (VFE) CARD (5 Channels) Very Front End (VFE) CARD (5 Channels) Very Front End (VFE) CARD (5 Channels) Very Front End (VFE) CARD (5 Channels) Very Front End CARD (VFE) 5 Channels Crystal Front End Card (FE) 25 Channels 14 bit Channel Data Trigger Primitives (Continuous) Data (on Level 1) GOH: Optical Digital Data Transmission
GRI M. Diemoz - INFN Roma Integrazione - 2 Front End Electronics LVRLVR VFEVFE VFEVFE VFEVFE VFEVFE VFEVFE Mother Board HV in Power in Digital Voltage Distribution Analog Voltage Distribution Trigger Fiber(s)Data Fiber Flexible Connection to APD’s / VPT’s Motherboard con kapton VFE LVR board FE Radicale cambio di disegno nel Torre di trigger
GRI M. Diemoz - INFN Roma Integrazione - 2 Produzione e test elettronica di serie “on detector” ben avviata Chip testing for EB nearing completion
GRI M. Diemoz - INFN Roma Integrazione TT per SM Sequenza operazioni: 1.Installazione VFE, LVRB e FE 2.Test TT singola (test pulse) Rumore ~ 1 ADC count (45 MeV ) 3.Installazione token rings e test 4.Installazione GOH e patch panel fibre ottiche e test 5.Distribuzione LV e servizi 6.Test con laser verde: cristalli e APD
GRI M. Diemoz - INFN Roma Intercalibrazione iniziale Misure sistematiche laboratorio (qualifica cristalli): misura intercalibrazione al 4% Test agosto 2004 su M1 ed estrapolazioni Montecarlo su M2, M3, M4: misura coefficienti intercalibrazione con precisione del 3% con 2 settimane/SM di presa dati SM10 all xtals: 4.0% 0.1% SM10-M1 xl con errore stat. cosm. < 2%
GRI M. Diemoz - INFN Roma Intercalibrazione cosmici Edge taggers Trigger counters focal plane 4cm below SM ~20 cm above SM 1.Incline along eta by deg. (to increase statistics in M4) 2.Selective quasi-pointing trigger with edge taggers 1. Rate +30% in M4, -20% in M1 2. Spectrum more homogeneus Guadagno APD x 4 Selezione eventi con tagli di isolamento SM inclinato di 10 °
GRI M. Diemoz - INFN Roma Calibrazione cosmici Cosmic ray set-up is progressing –Scintillators for telescope have been selected, cut and equipped by IHEP team –SM support with 10 º inclination being designed (Rome). Studio fattibilità e test preliminare: Milano Set up generale: CERN DAQ: CERN, Lisbona, Milano Meccanica per inclinazione: Roma Monitor on line: Milano e Trieste Simulazione a analisi dati: Milano
GRI M. Diemoz - INFN Roma DB di condizione contiene le condizioni del detector dal Detector Control System (DCS), dal DAQ/TR, dai run di calibrazione (Piedistalli, Laser Monitoring, Test-Pulse, …) Schema del database definito e testato con dati del test- beam di 1 SM del 2004 (Roma, Minnesota) Piano di usare questo schema per calibrazione cosmici ad H4 e magnet test 2005 Effettuate prove di lettura DB da ORCA Calibrazione cosmici / ECAL Data Base
GRI M. Diemoz - INFN Roma Schema DB CMS Configuration Conditions Calibration O ffline R econstruction C onditions DB ON line subset Equipment Configuration Conditions Create rec conDB data set Offline Reconstruction Conditions DB OFfline subset Master copy Bat 513 O nline M aster D ata S torage Schema from Frank Glege 1 PC at the test-beam with ORACLE (data from DCS, monitoring, Token Ring, …) for cosmic ray SM calibration 1 account at the IT ORACLE server for off-line database H4 (cosmics and test-beam) ECAL DB schema per cosmici
GRI M. Diemoz - INFN Roma Stato impegni INFN PRODUZIONE GRIGLIE (RM): TERMINATA 05/03 (36X4=144 PEZZI + spares) PRODUZIONE SUPER BASKETS (RM) : TERMINATA 06/04 (36 SB + spares) PRODUZIONE PS HV APD (RM):TERMINATA 12/03 (18 CRATE, 144 BOARD + spares) PRODUZIONE CAVI HV (RM): IN CORSO (80%) SISTEMA DI RAFFREDDAMENTO (MI): PRODUZIONE DI SERIE IN CORSO (3 SM/mese) MOTHERBOARD (TO): GARE CONCLUSE, PRODUZIONE E VALIDAZIONE PROTOTIPI OK, PRODUZIONE FINALE AVVIATA
GRI M. Diemoz - INFN Roma RAFFREDDAMENTO: Produzione in fonderia delle barre di raffreddamento finita Lavorazione barre 50% Assemblaggio cooling blocks 5 SM consegnati, 3SM/mese in corso Housing 2SM consegnati, segue consegna VFE Taglio laser Armaflex (INFN Genova) completo < fine maggio Raffreddamento / Motherboards MOTHERBOARDS: 3 Lotti da 1 SM di kapton consegnati da ditta ECS (Vicenza) SM11, SM5, SM16 Preserie di 80 MB da SEISYSTEM (Massa C.) SM5 Inizio serie assemblaggio SEISYSTEM SM16 (meta’ maggio 05) 3 SM/mese
GRI M. Diemoz - INFN Roma Conclusioni La produzione dei cristalli è la spada di Damocle Forte impegno per la validazione dei cristalli SIC Mezzo Barrel “bare” fatto (30600 cristalli = L3_ECAL_BGO*3) Integrazione SM quasi a regime su 3 linee parallele Impegni costruttivi INFN: in dirittura di arrivo Forte attività in crescita su: Gestione dati e ricostruzione Calibrazioni in situ Studi di Fisica: W, Top, Higgs, BSM