1
PLATO Mission: TOU Phase B/C1 preliminary KO meeting
December 12 th, 2016
2
Summary Contractual section (ASI, Leonardo, TAS-I, MLT)
Contract and Technical Annex Deliverable Planning Technical Section ( ESA,ASI, Leonardo, UBE, INAF) Optical Design Mechanical Design Thermical Design Project Team WBS Product Tree Risk analysis PLATO – KO meeting, ASI Ottobre 2016
3
Contractual Section
4
Milestone KO Offerta Industriale Fase B/C1 del programma PLATO per la realizzazione dei telescopi TOU Contenuto della presentazione Questa presentazione si riferisce alla milestone Kick Off del contratto ASI N. “Attività industriali di Fase B/C1 del programma PLATO per la realizzazione dei telescopi. contratto ASI N. CIG DBF CUP Data KO Obiettivi della milestone 4
5
PLATO TOU Partnership Responsibility
Company Responsibility PLATO phase B/C1 LDO Prime for PLATO subsystem TOU phase B/C1 activities Program Management and Product Assurance System Responsibility Design, Production and Testing Responsibility TAS-I Subcontractor Responsible for Thermal Engineering and MTD production MLT Production, Figuring and Polishing of L1 lens and protection windows Prime Leonardo System MTD Thermal Engineering TAS-I MAIT Lente L1, Finestra MLT 5
6
Albero del prodotto del programma PLATO / telescopi TOU
N-TOU (1-4): In blu sono indicati i sottosistemi di competenza di LDO (produzione e/o integrazione), in arancione i sottosistemi prodotti da UBE e forniti a LDO come AFE, in giallo i sottosistemi forniti da TBC nel PMC e forniti a LDO come AFE. 6
7
Albero del prodotto del programma PLATO / telescopi TOU
F-TOU: In blu sono indicati i sottosistemi di competenza di LDO (produzione e/o integrazione), in arancione i sottosistemi prodotti da UBE e forniti a LDO come AFE, in giallo i sottosistemi forniti da TBC nel PMC e forniti a LDO come AFE, in grigio il sottosistema prodotto da UST e fornito a LDO come AFE. 7
8
WBS del programma PLATO / telescopi TOU
8
9
Nominativo aggiornato
Team di progetto Nominativo aggiornato Ruolo nel progetto Responsabile WP G. Benedetti Program Manager 1-2AA G. Bonetti Contract Officer F. Agnoloni Project Control P. Bruno Configuration & Data Management M. Picchi Product Assurance Manager 1-2ACA F. Era Material & Processes / Cleanliness PA 1-2ACD Novi Instrument Project Leader (PEM) 1-2ADA E. Di Carmine Structural Engineering Responsible 1-2ADH A. Taiti Optical Design Responsible 1-2ADK G. Pastorini AIV Responsible 1-2ADV A.Novi ASI AFE Engineering 1-2ADX M. Marinai AIT Responsible 1-2BA A.Caruso Manufacturing & Assembly 1-2BD M. Taiti MGSE Responsible 1-2KB 9
10
Fornitura contrattuale: documenti (1/5)
10
11
Fornitura contrattuale: documenti (2/5)
11
12
Fornitura contrattuale: documenti (3/5)
12
13
Fornitura contrattuale: documenti (4/5)
13
14
Fornitura contrattuale: documenti (5/5)
14
15
Fornitura contrattuale: modelli matematici
MATHEMATICAL MODELS CODICE PRODOTTO FORMATO EVENTO NOTE MM-001 CAD Model STEP PDR, STM-DR, MTD-DR Con documento descrittivo in inglese MM-002 Optical Model ZEMAX MM-003 Finite Element Structural Model (FESM) of BA NASTRAN MM-004 Geometrical and Thermal Mathematical Model (GTMM) of BA ESATAN 15
16
PLATO phase B/C1 Schedule
HARDWARE OGGETTO DI FORNITURA CO DI CE PRODUCT MODEL SCHEDULE Date (T0 = dec 12, ) HW-1 Dummy of OMG1 STM T m Dec 12, 2017 HW-2 Dummy of OMG2 Dec 12, 2017 HW-3 Dummy of OMG3 HW-4 Dummy of OMG4 Dec 12, 2017 HW-5 Dummy of OMG5 HW-6 Dummy of OMG6 HW-7 Dummy of l BA HW-8 2 dummies of BA (Batch 1) MTD T m Aug 12, 2018 HW-9 8 dummies of BA (Batch 2) T m Sept 12, 2018 HW-10 8 dummies of BA (Batch 3) T m Oct 12, 2018 HW-11 8 dummies of BA (Batch 4) T m Nov 12, 2018 HW-12 8 dummies of BA (Batch 5) T m Dic 12, 2018 HW-13 EM Model EM Dic 12,2018 Legenda: BA Baffle Assembly 16
17
Fornitura contrattuale a carico ASI
DOCUMENTI E MODELLI MATEMATICI CODICE TITOLO SCHEDULE Data Consegna DEL-ASI-001 Modello ottico di riferimento (ray tracing) in formato Zemax e .stp Offerta Aggiornamento al KO 12 dic 2016 DEL-ASI-002 Disegno meccanico del TOU KOM 12 dic 2016 DEL-ASI-003 Modello strutturale del TOU DEL-ASI-004 Modello termico del TOU HARDWARE DEL-ASI-005 MGs(1-6) per STM T0 + 9 mesi 12 set 2017 DEL-ASI-006 STRUCT per STM DEL-ASI-007 STRUCT per EM T mesi 12 dic 2017 DEL-ASI-008 TOU TCS per EM DEL-ASI-009 MGs(1-6) per EM 17
18
PLATO – Milestone contrattuali
Piano milestone Luogo Data T0 + m Data yy-mm TOT KO Kick-off ASI T0 RA1 RA1 / D-SRR Delta System Requirements Review 2 RA2 RA2 / PDR Preliminary Design Review LDO 8 RA3 RA3 / STM-DR STM Delivery Review TASI 12 RA4 20 RA5/RF RA5 / MTD-DR + EM-DR 24
19
PLATO – aspetti contrattuali
Contratto: in via di perfezionamento RTI: Atto stipulato Fidejussione Altri topics …
20
Technical Section
21
PLATO : the mission PLATO (PLAnetary Transits and Oscillations of Stars) M3 is the mission of the ESA Cosmic Vision program dedicated to the study of the physical structure of mass planets like Earth. The 34 telescopes of PLATO, designed by INAF researchers in collaboration with researchers at the University of Bern, are one of the Italian contributions to the mission. PLATO will be launched in 2024 with a Soyuz-Fregat from Kourou, and will operate for eight years observing the cosmos by the L2 Lagrangian point.
22
PLATO : international cooperations
The PLATO mission provides a long international collaboration under the ESA Cosmic Vision program. The figure illustrates the international cooperation at the payload level. The Italian participation in the PLATO project has been defined inside the PMC (Plato Mission Consortium). The implementation of TOU subsystem involves three scientific institutes: INAF (Italy), University of Bern (Switzerland) and Stockholm University (Sweden). The HW supply by the partners of the University of Bern (UBE) and the University of Stockholm (FSO) which will contribute to the implementation of TOU is organised as follows: The mechanical parts of the TOU (STRUCT), relating to flight patterns, the spares and some of the models of development. The coating of the two telescopes Fast window (blue and red, respectively) will be filed and qualified by UST. As for the models related to Phase B / C1 covered by this Technical Annex, they do not involve the use of F-TOU filters, so there will be AFE related supplies.
23
PLATO TOU Partnership Responsibility
Company Responsibility PLATO phase B/C1 LDO Prime for PLATO subsystem TOU phase B/C1 activities Program Management and Product Assurance System Responsibility Design, Production and Testing Responsibility TAS-I Subcontractor Responsible for Thermal Engineering and MTD production MLT Production, Figuring and Polishing of L1 lens and protection windows Prime Leonardo System MTD Thermal Engineering TAS-I MAIT Lente L1, Finestra MLT
24
PLATO : TOU schematics
25
PLATO : Baffle Assembly
26
PLATO Tree The Product Tree was detailed according to Technical Specifications provided By ASI TOU (Telescope Optical Units) x 34: F-TOU Blue F-TOU Red N-TOU (x 32) TOA (Telescope Optical Assembly) x 34: common parts of TOU’s Optics (six types Lenses) Structure Thermal HW Cube Assembly
27
PLATO/ TOU Product Tree N-TOU (1-4)
Blue: Leonardo Items (Production and Integration) Orange; UBe (AFE) Items Yellow: PMC (AFE) Items . 27
28
PLATO/ TOU Product Tree F-TOU
Blue: Leonardo Items (Production and Integration) Orange; UBe (AFE) Items Yellow: PMC (AFE) Items Grey: USt (AFE) Items 28
29
PLATO : TOA Tree
30
Nominativo aggiornato
Project Team Nominativo aggiornato Ruolo nel progetto Responsabile WP G. Benedetti Program Manager 1-2AA G. Bonetti Contract Officer F. Agnoloni Project Control P. Bruno Configuration & Data Management M. Picchi Product Assurance Manager 1-2ACA F. Era Material & Processes / Cleanliness PA 1-2ACD Novi Instrument Project Leader (PEM) 1-2ADA E. Di Carmine Structural Engineering Responsible 1-2ADH A. Taiti Optical Design Responsible 1-2ADK G. Pastorini AIV Responsible 1-2ADV A.Novi ASI AFE Engineering 1-2ADX M. Marinai AIT Responsible 1-2BA A.Caruso Manufacturing & Assembly 1-2BD M. Taiti MGSE Responsible 1-2KB 30
31
Plato/TOU WBS 31
32
PLATO: phase B/C1 (1/3) Development B1 Phase Diagram
33
PLATO: phase B/C1 (2/3) MTD Model Development Diagram
STM Development Diagram
34
PLATO: phase B/C1 (3/3) EM Development Diagram
35
Risk Analysis (1/2) 35
36
Risk Analysis (2/2) 36
37
PLATO phase B/C1 Schedule
HARDWARE OGGETTO DI FORNITURA CO DI CE PRODUCT MODEL SCHEDULE Date (T0 = dec 12, ) HW-1 Dummy of OMG1 STM T m Dec 12, 2017 HW-2 Dummy of OMG2 Dec 12, 2017 HW-3 Dummy of OMG3 HW-4 Dummy of OMG4 Dec 12, 2017 HW-5 Dummy of OMG5 HW-6 Dummy of OMG6 HW-7 Dummy of l BA HW-8 2 dummies of BA (Batch 1) MTD T m Aug 12, 2018 HW-9 8 dummies of BA (Batch 2) T m Sept 12, 2018 HW-10 8 dummies of BA (Batch 3) T m Oct 12, 2018 HW-11 8 dummies of BA (Batch 4) T m Nov 12, 2018 HW-12 8 dummies of BA (Batch 5) T m Dic 12, 2018 HW-13 EM Model EM Dic 12,2018 Legenda: BA Baffle Assembly
38
PLATO phase B/C1 Schedule
39
PLATO phase C2/D Schedule
HARDWARE OGGETTO DI FORNITURA EVENT MODEL SCHEDULE Date N-TOU QM Oct 7, 2020 F-TOU 8 N-TOU FM Nov 11, 2021 2 F-TOU Apr 11, 2022 May 9, 2022 Aug 29, 2022 Dec 19, 2022
40
PLATO phase C2/D Schedule