Presentazione preventivi 2012 INFN Pisa M. Sozzi – 20/6/2011.

Slides:



Advertisements
Presentazioni simili
LHCf Status Report Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento di Fisica.
Advertisements

CMS RPC R&D for phase 2 Two types of upgrades proposed for the CMS RPC muon system: 1.Aging and longevity: installed in 2007, must continue to operate.
Opzioni tecnologiche per l’elettronica di front-end del Gigatracker Angelo Rivetti – INFN Sezione di Torino.
E. Iacopini, CSN1: 5 febbraio 2007 It's a long long way to Tipperary, But my heart's right there. Argomenti:  Stato degli R&D i) GigaTracker ii) Veti.
R.N. - Referees LHCB-CSN1 09/021 LHCB : proposte dei referees Giulio D’Agostini Chiara Meroni Rosario Nania.
CMS RPC R&D for phase 2 Two types of upgrades proposed for the CMS RPC muon system: 1.Aging and longevity: installed in 2007, must continue to operate.
Attivita` di TileCal 2013 C.Roda Universita` e INFN Pisa Riunione referees ATLAS Roma 1 C.Roda Universita` e INFN Pisa.
G. Martellotti Roma RRB 16 Aprile Presentazione M&O cat A (per LHCb i M&O cat B sono gestiti autonomamente e non sono scrutinati fino al 2005/2006)
1 M&O cat A - consuntivo provvisorio modifica del preventivo 2004 M&O cat B ancora non sono previsti. (saranno presentati al RRB di Aprile) Profili.
ATLAS Status Report S. Patricelli 6 aprile Sommario Commissione Scientifica Nazionale I 5-6 aprile 2004 S. Patricelli Highlights and concerns dei.
F. Marchetto – INFN- Torino GigaTracKer: status report 25 Maggio Update su infra-structures 2. Stato del cooling 3.Bump-bonding e thinning 4. Stato.
MUG-TEST A. Baldini 29 gennaio 2002
CSN1, 17 settembre 2002 COMPASS prospettive verso la fase 2: tempi ed impegni italiani previsti F. Bradamante attivita’ della collaborazione per la fase.
MS - NA62 TDAQ INFN – Settembre 2011 TDAQ in generale Distribuzione clock/trigger: progetto definito, moduli finali in arrivo (?), installazione prevista.
MS - NA62 TDAQ INFN – Maggio 2012 NA62 TDAQ status report M. Sozzi Incontro con referee INFN CERN – 25 Maggio 2012.
E. Iacopini CSN1: Torino 25 settembre E. Iacopini CSN1: Pisa 28 maggio 2012 Sommario: Verso il Technical Run di fine ottobre; Report sull’avanzamento.
News LHC recommissioning is continuing Sucessfully achieved so far 4 TeV beams, 0.6 m beta* (at least with few bunches) Some beam splashes last week; still.
MEG (Torino 25 settembre 2012: A.Baldini) Stato dell’esperimento e generalita’ sull’upgrade.
MS - NA62 – Luglio 2013 NA62 M. Sozzi Presentazione preventivi INFN Pisa – Luglio 2013.
Interessi e richieste finanziarie per IBL. 2 IBL Lay-out 2  Since IBL is an additive layer, its radiation length has to be extremely small  Geometry.
Richieste IFR 2011 Roberto Calabrese Università e INFN – Ferrara Marzo 2011.
TGC upgrade for SLHC (ATL-P-MN-0028 ) Fra le parti più colpite dall’aumento di rate previsto a SLHC ci sono le Small Wheels Le TGC con catodo a bassa resistività.
NA62 (Pre)-preventivi M. Sozzi INFN Pisa 29 Giugno 2016.
MM news & status -Final Design Review -NA for NSW -altre attività MM.
1 CSN I, ROMA 30-31/1/2012 AGPSilvia DALLA TORRE ERC Advanced Grant 2012 : PROPOSAL “Advanced Gaseous Photon detectors for Hadron Physics Investigation”:
1 Bern ITP, Birmingham, CERN, Dubna, Ferrara, Fairfax, Firenze, Frascati, IHEP, INR, Louvain, Mainz, Merced, Napoli, Perugia, Pisa, Roma, Roma 2, San Luis.
Enrico Iacopini Ferrara, 15 settembre 2009 Sarò breve.
COMPASS Relazione dei referee P. Cenci P. Branchini M. Sozzi.
Michele Iacovacci (Napoli),
Run 3 Statistics EEE Run coordination meeting esteso alle scuole
Che c’è di nuovo… E. Iacopini, CSN1 Presidenza INFN 30 marzo 2010.
Lepton Flavour MEG A. Baldini CSN1 22 Nov. 2011: GGI.
Compositi per ATLAS Overview del processo per la costruzione supporti per ATLAS Tempistica.
Analisi Impegni per Upgrade (dal DB INFN )
MEG (Pisa 29 Maggio 2012: A.Baldini)
LHCB : proposte dei referee
Consiglio di Sezione: preventivi 2015, 15 luglio 2014
Amarcord … E. Iacopini: Presidenza INFN, 3 giugno 2013.
C.Bini, P.Paolucci, A.Tricomi 18/09/2008
Calorimetro LAR ATLAS Italia Roma 28 novembre 2008
Richieste 2017 HMPID e LHC_IF
P326 (+ NA48/n) Relazione dei referee
Presentazione preventivi
The FOOT Calorimeter No TOF, high density and good energy resolution -> BGO TOF asks for 1.2 m lever arm -> R = 20 cm with 100 angular aperture of the.
Gagliardi Università degli Studi e INFN Torino
RD_FASE2: Mechanics and Cooling Pixel R&D Projects Meeting Milano, 8 giugno 2015 Simone Coelli, Andrea Capsoni, Carlo Gesmundo, Mauro Monti, Ennio Viscione.
Analisi dei dati dell’Esperimento ALICE
Status Report di E. Iacopini CSN1- Bari 21 sett
Waveform Digitizer Review
relazione referee settembre 2009 p. branchini, s.ragazzi, m.sozzi
LHCB : proposte dei referees
Gigi Cosentino - LNL 20 ottobre 2016
UA9 Relazione dei Referee
TOTEM: rapporto dei referee
P-ILC F. Bedeschi INFN-Pisa P-ILC Preventivi 2012 Preventivi 2012
Accelerator Disision March 3rd 2015
Highlights del meeting ESPP di Cracovia Settembre 2012 (FISICA DI G1)
M.Biasini, P. Checchia 18 Settembre 2008 Riunione CSN1
SuperB – Richieste Sblocchi 2008
Atlas Milano Giugno 2008.
Gianluca Lamanna & Marco Sozzi (Univ. Pisa) Preventivi
P. Giannetti per il gruppo FTK
Consiglio di Sezione INFN Perugia
Consiglio di Sezione INFN Perugia
Il trigger per muoni dell’esperimento CMS
Assegnazioni/Residuo 2004
NA62 Pisa ( Approvato Sett. 2009) Due impegni principali di Pisa:
Study of Bc in CMSSW: status report Silvia Taroni Sandra Malvezzi Daniele Pedrini INFN Milano-Bicocca.
Preliminary results of DESY drift chambers efficiency test
M. Sozzi - Presentazione preventivi INFN Pisa – 2 Luglio 2019
Transcript della presentazione:

Presentazione preventivi 2012 INFN Pisa M. Sozzi – 20/6/2011

Babar/Belle: B d (& D, tau) CDF/D0, LHCb: D, B d, B s MEG: LFV KOTO, NA62: rare K decays Future B factories (KEK + SuperB) ProjectX at Fermilab: m2e, rare K Flavour physics – Sensitivity frontier NA62 unique physics goal: |V td | to 8% without input from lattice QCD (in 2 years of data taking) NA62 unique technique: high momentum unseparated K + beam with beam momentum spectrometer and extensive particle ID

K      in SM  BR(SM) = (8.22 ± 0.75) ×  J. Brod, M. Gorbahn, E. Stamou arXiv:   |V td | / |V td | ≈ 0.4  P c /P c  0.7  BR /BR   |V cb | / |V cb | (0,0) (1,0) P c   (  ) |V td | ~(BR ) 1/2 3 % ~2 % (mostly  m c ) 62 % BNL 8% aim of NA62 (2y)

Birmingham Bristol Glasgow Liverpool Ferrara Firenze LNF Napoli Perugia Pisa Roma I Roma II Torino UC Louvain Mainz George Mason SLAC UC Merced TRIUMF San Luis Potosi IHEP INR JINR CERN Bratislava Sofia

Full NA62 data set: precision will be improved from 0.5% to 0.4%. R K = (2.487 ± stat ± syst )  10 –5 R K = (2.487 ± 0.013)  10 –5 R K = (2.487 ± stat ± syst )  10 –5 R K = (2.487 ± 0.013)  10 –5 Errors in momentum bins are partially correlated SM PLB B698 (2011) 105 World ave  R K  10 5 Error PDG  % Today  %

Measure Kaon: Time Angles Momentum INFN 6 Target Total Length 270m Decay Region 65m Gigatracker (GTK) LAV: Large Angle Photon Veto RICH LKr SAV Small Angle Veto MUV CEDAR Straw Tracker CHOD Charged Hodoscope Beam Line + Infra. UK Sofia INFN Mainz CERN Mexico US IHEP INR IHEP INR Belgium JINR CERN SPS primary p: 400 GeV/c Unsepared beam: 75 GeV/c 750 MHz  /K/p (~6% K + ) CERN CHANTI INFN Trigger & DAQ:

NA62 status

Beam line and LAV1-5 LKrMUVRICH 2 Straw 1 Straw 3 Straw 4 Straw LAV 1-5 LAV 9-11 LAV 6-8 CEDAR GTK 3 vacuum Vessel are positioned MNP33 Magnet Situation today CHOD + LKR (NA48) Installation in 2011 first Vacuum test On first section Expected for Sept. K12 Beam Line Prepare Support for Beam Magnet Beam Dump Situation in Dec. 2011

Completion with STRAW and LAV LKrMUVRICH 2 Straw 1 Straw 3 Straw 4 Straw LAV 1-5 LAV 9-11 LAV 6-8 CEDAR GTK Installation Summer 12 Situation in Sept MNP33 Temp. RICH Beam Pipe ?? Complete Vacuum Pumping Ready for the Technical Run Module Chamber

JFMAMJJASONDJFMAMJJASOND Beam Cedar GTK Photon Veto RICH STRAW MUV RUN LAV 1-5 VesselNose ASIC Design Read-Out Board Prod. Cooling Studies Bond. + Ass. Test Cooling DesignCool. Constr. + Test Install M6-8 LAV 6-8 LAV 9-11 Install. L 12 Install. Installation 10TD Status + NA62 Schedule Install M9-11 M3-5 Construction Vessel Beam pipe Constr. Mod. 1 Construction Mod. 3,5+7 M1+2 Install. MUV 1,2 +3 Tech. Run Construction Note: not all milestones are shown on this planning Installation Milestones Dry Run Technical Run NA62 Schedule (Overview for main items only ) TDAQ

NA62 Pisa GRUPPO: 11.9 FTE ATTIVITA’: Ruolo guida per TDAQ Partecipazione a costruzione LAV Progettazione meccanica sistema MUV Simulazione MC

12 LAV stations mounted along 120 meter decay region 6 meters apart 4 different types: –160, 240 blocks; 5 layers in vacuum –240 blocks; 4 layers in vacuum –256 blocks; 4 layers in air Angular coverage 8-50 mrad Inefficiency < from few hundred MeV to 35 GeV 2500 lead glass blocks (OPAL barrel calorimeter) Efficiency measurements with electron beams in 2007: 1-  <10 -4 for 200 MeV<E<500 MeV A1-A11 Vacuum LAV – Large Angle Photon Vetoes

13 A3 shipped at CERN beginning of December 2010, some problems during the transport (see later) A4 completed tested and ready to be shipped at cern, we are currently revisiting the transportation procedure A5 arrived at LNF February 18, actually 3 out of 5 layers are mounted and tested, we foresee to complete it by mid April (2 months delay respect to the schedule)

14 A6-A8, A11 Bidding procedure closed adjudicated by Fantini factory, all drawings have been revisited and the material has been procured. A6 is actually scheduled and will be shipped to LNF end of May. We foresee to build and test A6-A8 during 2011 A6-A8 5 layers ∅ 259 cm A11 4 layers ∅ 299 cm

15 Recall: A9, A10 have same dimensions as A11, but are made of stainless steel A12 has open geometry—design is totally different A9-A10 drawings will be revised in the next months and we will start the bidding procedure, the idea is to start vessels construction by the end of 2011 A6-A8 5 layers ∅ 259 cm A11 4 layers ∅ 299 cm

16 A3: Due to bad weather conditions (M.Blanc tunnel was closed) the transport took 3 days. Even if all precautions where taken, we insulated the vessel by means of fiberglass cover, the temperature in the vessel reached 5 degrees after 2 days in the snow. 10 blocks were broken during transport! Fractures are most likely from thermal stress Likely from re-heating from ~4 ∘ to 15.5 ∘ at ECN3 (cooling was much slower) 9 of 10 blocks on layers most exposed to ambient temperature We have already started A3 repair work in ECN3 6 of 10 blocks repaired Unfortunately A2 experienced a significant temperature gradient: A2 was shipped to CERN end of JULY 1) All the blocks were checked at CERN before the test beam and they were ok 2) The idea was to store all the LAVs in building 185. We were ensured that 185 was air conditioned during summer and heated during winter (including shutdown). A2 was stored in building 185 at the end of August. 4) We went to inspect A2 in February and found 22 blocks broken !! 5) The heating in 185 was switched off without notice during the winter shutdown and never restarted 6) From now on all the LAVs will be stored in ECN3 and an appropriate temperature monitor has been implemented

RICHMUVCEDARLKRSTRAWSLAV L0 CTP GbE switch PC CDR L0 trigger Trigger primitives Data EB 1 MHz O(10 MHz) O(KHz) NA62 TDAQ - OVERVIEW 1 MHz L0 L1/2 O(<1ms) 2K 1K 200 8K 13K 2.5K 60K

NA62 Pisa TDAQ Il gruppo ha subito un pesante ridimensionamento: In un anno: –3 FTE dedicati di grande esperienza Tecnologi (a tempo parziale) << richieste Richiesto art. 23, ottenuto 2222, assegnato, rinuncia, nuova assegnazione [nessun effetto su manpower netto] Praticamente nessun supporto da altri gruppi di NA62 Attivita’ fondamentali per la collaborazione: - Sistema integrato di trigger e readout basato su TDC (per 80% dei rivelatori INFN e non) - Upgrade schede madri comuni (per quanto sopra e anche per altri sistemi) M. Sozzi responsabile TDAQ NA62 Fine sviluppo 2011 Produzione e test su fascio 2012 Installazione e commissioning 2013

Pisa TDAQ: Scheda TDC Scheda figlia ( ps) per la maggior parte dei sistemi di readout di NA62 R&D per utilizzo in readout di EEE per telescopi raggi cosmici

Pisa TDAQ: Scheda TDC Storia: - Progetto non portato a termine dal progettista (G. Magazzu) - Parzialmente modificato da ass. ric. “in prestito” (A. Burato) - A. Burato lascia INFN con 1 giorno di preavviso (5/2011) Stato attuale: - Prototipi versione finale a giorni (S. Galeotti), cavi OK - Esiste versione di firmware “funzionante” (sotto test, non completa) ma completamente “as is” - “Richieste minime” firmware (1/2009) non completate - Sistema di test “automatizzato” in preparazione - Hardware per test produzione da disegnare e costruire Futuro: - Produzione ~14 schede tra 1 mese - Distribuzione nella collaborazione per test - Lancio produzione finale (~100) entro fine 2011

Optical trigger to TELL1 Trigin/out from/to PG to LTU module Signal conversions Data to PC through GBE TDCB TESTING

Pisa TDAQ – TEL62 Scheda madre per la maggior parte dei sistemi di trigger e readout di NA62 16 layer, impedenza controllata

Storia: - Sostanziale ridisegno della scheda TELL1 di LHCb - Scheda complessa - Disegno completato a Pisa (F. Spinella, E. Pedreschi) - Layout al CERN (dic 2010-feb 2011) Stato attuale: - 1 prototipo (2 PCB) a Pisa da - Test elettrici OK - Compatibilita’ schede figlie OK - Inizio sviluppo firmware - Per ora nessun supporto da altri gruppi Futuro: - Tutti i test funzionali - Secondo prototipo (modifiche minime per ora) - Produzione ~10 schede entro Produzione (~100) 2012, coinvolgimento Roma TV Pisa TDAQ – TEL62

Processore L0 (resp. INFN): ancora poco progresso - Pisa non coinvolta in implementazione, come richiesto (ma disegno concettuale) - Studi su implementazione in PC iniziati (FE/CERN) - Responsabilita’ software: Ferrara - Responsabilita’ hardware: non ancora identificata - Milestone: demonstrator fine 2011 Rete (per readout/trigger/L0): esiste expertise a Pisa (non INFN): identificare modo per poterla sfruttare R&D: studio implementazione trigger HW con GPU - Ongoing - Ricostruzione online anelli RICH - Studio di reiezione fondo in camere straw a L1 Simulazione: ripreso lavoro Monte Carlo a Pisa (obiettivo: rate di L1/L2, decadimenti rari) Pisa TDAQ: Altro

Pisa TDAQ – 2012 Il problema di manpower sta condizionando il mantenimento degli impegni INFN. Per Pisa TDAQ: - Completamento firmware TDCB - Produzione e test (test bench) TDCB - Firmware TEL62 - Produzione TEL62 Produzioni fine 2011/2012, ma acquisto componenti critici): O(200KE) finanziamento CORE “Dry run” per TDAQ a primavera 2012 (pesante coinvolgimento di Pisa) Pisa e’ il gruppo di riferimento per il TDAQ. E’ indispensabile maggiore manpower e supporto elettronico qualificato, per il completamento dell’hardware, lo sviluppo del firmware e il test Con il manpower attuale la schedule subira’ ritardi

Richieste 2012 TDAQ: Secondo prototipo TEL62: 10 KE (sub judice) Sistema di test per TDCB: 10 KE Materiale laboratorio: 8 KE (Sonda diff. + PC sviluppo firmware) CORE 2012: 450 KE previsto per TDAQ-I (Produzioni) di cui 150KE Pisa Possibile rimodulazione sul 2013 Dry run (~1 mese): 4 FTE Manpower necessario: F. Spinella, E. Pedreschi (TEL62 ma anche TDCB) +1 Fisico/tecnologo per firmware +0.3 FTE per gestione produzione +Coinvolgimento esperto reti LAV: CORE 2012: 80 KE (Costruzioni), metabolismo, trasporti, installazione Manpower necessario: Turni a LNF LAV + TDAQ: Technical run (~3 mesi): 3 FTE

NA

Richieste 2012 (in via di finalizzazione)

SPARES

LAV schedule

Recent publications

World average  R K  10 5 Precision PDG  % Today  % Other limits on 2HDM-II: PRD 82 (2010) SM with 4 generations: JHEP 1007 (2010) 006. b  s  excluded

Pixel Cell Hit Arbiter Pixel matrix TDC: delay line, charge pump, encoder, fine hit Registers GigaTracker

Vacuum Straw Chambers

17 m Beam Pipe Mirrors Separate pions from muons <1% level between 15 and 35 GeV/c Track time at 100 ps level Partecipate in the L0 trigger Neon as Cerenkov radiator mosaic of mirrors (17 m focal length) two spots with PM (1000 PM per spot) beam pipe passing through PM lodging disk 5/4/ RICH