Perugia 11/12/20021 AMS Data Handling e INFN P.G. Rancoita
2 AMS Ground Segment Data flow in AMS-02 High Rate (Scientific + Calibration) : 3-4 Mbit/s Slow Rate (House Keeping) : 16 kbit/s NASA ancillary data : 1 kbit/s Total Volume : GB/day TB/year
3 AMS Ground Segment Data volume in AMS-02 Archived Data 1. Event Summary Data : 44 TB/year 2. Event Tag : 0.6 TB/year 3. Total (+Raw and ancillary) : TB/year Data on direct access 1. Event Summary Data : 8.3 TB/year 2. Event Tag : 0.6 TB/year Total data volume (3 years): 180 TB Namely 180 GB/day
4 Events and Ev. rate Exp rate of average accepted ev. about 200 Hz, this means in 3 ys about (1.5-2)x10^10 evs Typical reconstructed ev. length less than about kB. Total storage for ESD about 130 TB
5 AMS Ground Segment Data budget in AMS-02
6 AMS Ground Segment: Data budget in AMS-02 AMS Ground Centers Science Operations Center POCC AL AMS Remote center RT data Commanding Monitoring NRT Analysis NRT Data Processing Primary storage Archiving Distribution Science Analysis MC production Data mirror archiving External Communications Science Operations Center XTerm HOSC Web Server and xterm TReK WS commands Monitoring, H&S data Flight Ancillary data AMS science data (selected) TReK WS voiceloop Video distribution Production Farm Analysis Facilities PC Farm Data Server Analysis Facilities GSE D S A e T r A v e r GSE Buffer data Retransmit To SOC AMS Station AMS Station AMS Station GSE MC production cmds archive AMS Data, NASA data, metadata
7 AMS Ground Segment AMS-02 Ground Facilities Marshal MSFC JSFC / MSFC / MIT / CERN CERN Remote Center - Italian Ground Segment Laboratories
8
9 AMS Ground Segment Payload Operation and Integration Center (POIC) Marshall SFC (Huntsville -AL) Receives data from ISS Buffers data until retransmission to (A)SOC Forward monitoring and meta-data to POCC Transmits commands from POCC to AMS Runs unattended 24h/day, 7days/week Must buffer ~ 2 weeks of data 600 GByte
10 AMS Ground Segment Payload Operation Control Center (POCC) JSFC, MSFC, MIT, CERN Receives data from MSFC Monitors data and runs quality control program Process ~ 10% of data in near real time Originates and transmits commands to AMS through POIC Requires scientists on shift
11 AMS Ground Segment (AMS) Science Operation Center [(A)SOC] Complete Data Repository (Raw + Reco) Production of Reconstructed data Re-processing / Re-calibration of data Meta-data Repository and Command archive Production and management of MC events MonteCarlo Repository Scientific Data Analysis Facility
12 Archiving and Staging Analysis Facilities Data Server Cell #1 #2 #8 PC Linux 2x2GHz+ PC Linux 2x2GHz+ PC Linux 2x2GHz+ PC Linux 2x2GHz+ PC Linux 2x2GHz+ Tape Server PC Linux 2x2GHz+ PC Linux Server 2x2GHz, SCSI RAID Tape Server Disk Server Disk Server Disk Server Gigabit Switch (1 Gbit/sec) PC Linux 2x2GHz+ 2xSMP, (Q, SUN) AMS data NASA data metadata AMS Science Operation Center Computing Facilities Production Farm Disk Server Disk Server Simulated data MC Data Server
13 AMS Ground Segment AMS Italian Ground Segment (IGS) Get data (raw + reco + meta-data) from (A)SOC Complete Mirror and Meta-data repository: Master Copy of the full Data set Monte Carlo production (20%) Support local users community for Data Analysis
14 AMS Ground Segment AMS Italian Ground Segment
15 AMS Ground Segment Italian Ground Segment Facilities Italian Ground Segment Data Storage Complete mirror data and meta-data repository (IGSDS) namely the MASTER COPY of the full AMS Data Set Data Transfer Facility DTF Data Transfer Management and Survey DTMS Monte Carlo contribution: (20%)
16 AMS Ground Segment Data Transfer to IGS Involved: DTF, IGSDS, DTMS DTF (CERN): access Data at (A)SOC and transfer to IGSDS IGSDS (TBD): receive and store Data DTMS (Milano): watch over the Data transfer Network required: 32 Mbit/s
17
18 DATA Transfer Dev.
19 Data transfer New release of Data Transfer is running since 20 weeks. Stops are due only to power outages at CERN.
20 Data transfer production rate = 2.2 Mbit/sec Sustainable production rate = 8 Mb/sec (80% of available bandwidth) This thanks to a forking mechanism and bbftps efficient bandwidth usage Milano and CERN Data Transfer DBs consistency = 100% Data that has to be retransmitted= 0.2 %
21 Data transfer: present work Test bbftps variable TCP parameters (done) Release a new version of our bbftp (minor changes on authorization and error reporting) (done) Test system in a more reliable environment (no power outages…) Implement automatic recovery. Setup GUI (Graph. User Interface) to start/stop system Complete Web monitoring tools.
22
23 AMS Italian Ground Segment Data Storage at IGSDS Place: TBD Archived Data: 180 TB (3 years) On-line Data: ~ 2 TB (1-2 weeks)
24 Descrizione dei costi Costi relativi al Central AMS Ground Segment (POIC+POCC+(A)SOC)
25 Central Production Facility La Central Production Facility sara dedicata alla ricostruzione dei dati. La CPF sara fisicamente alloggiata presso il CERN e fa parte dell (A)SOC Le necessita per la CPF sono suddivise in storage e CPU (e DB servers).
26 HW e costi del Data Handling di AMS Per quanto riguarda la potenza di calcolo, si avra bisogno dellequivalente di: 50 dual 1.5 GHz boxes, 1 GB RAM, Processing storage: 10 TB ---Central Production Facility
27 Central Production Facility Ai costi e alle conoscenze attuali degli sviluppi dei costi, si prevede per la facility nel periodo un costo di CPF 350 KUS $ DB Servers 50 KUS $ Event Storage 200 KUS $
28 POCC, Marshall (POIC), Analysis Ai costi e alle conoscenze attuali degli sviluppi dei costi, si prevede un costo di Marshall 55 KUS $ POCC (x2) 150 KUS $ Analysis 55 KUS $
29 Spese Addizionali Spese per prototipi e initial set-up) 150 KUS $ Running costs & Upgrades 2007– KUS $ Totale (escluso personale) 1160 KUS $ Si attende che il 20% +IVA di questa circa venga da parte INFN : 277 k
30 Stime del personale per il Data Handling di AMS E in fase di formalizzazione la spesa per personale (oltre ai fisici) da dedicare al data handling per il periodo Il personale consiste in system administrators, SW and HW engeneers. Le stime in anni/uomo sono: POCC circa 8.5 (A)SOC circa 15.3 Users support group circa 15.6 (incluso personale dedicato ad item particolari quali lo storage) Totale circa 39.4/anni uomo Se si assume un costo di 50K/anno uomo si ottiene circa 1970 K, il cui 20% (circa 390 K) dovrebbe essere un contributo INFN
31 Descrizione dei costi Costi relativi all Italian Ground Segment, relativi a DTF, DTMS, IGSDS
32 DTF Il sistema di DATA TRANSFER avra un suo front-end INFN presso il CERN, con un sistema dedicato a prendere i dati e trasferirli in Italia al MASTER COPY repository Il sistema si basa su: Architettura Client/Server (SSL) Bbftp MySql
33 DTF cont. Per tale sistema sara necessario: 1 Server AMD 1.5 GHz 1.5 TB su disk raid (scsi) 32 Mb/s CERN IGS Costo inclusa la manutenzione e sostituzione dei server circa 50k +IVA mel periodo Richieste di banda: (4 R + 8 NT ) + (2 R + 4 NT ) rt + 2 (SR+CAS) = 20 Mb/s
34 DTMS High performance server, with fast CPU and high I/O throughput. I/O Buffer Capacity equivalent to 7 days of data taking to recover from any connectivity failure 1.5 Tbytes Network High speed network connections to CPF. Must be consistent with a flux of 3 days worth of data: 32 Mb/s Each facility (DTF and DTMS) costs about 27+VAT k up 2008
35 DATA STORAGE : Italian MASTER COPY 2 High performance servers, with fast CPU and high I/O throughput. I/O Buffer : Capacity equivalent to about 3 days of data taking to recover from any connectivity failure (0.5 Tbytes) On-line storage RAID system (1 Tbytes) Off-line storage : Tapes or similar (e.g.: LTO) 180 Tbytes. For instance LTO Off-line Robotics staging area: Depending on the robot solution adopted, it varies between a few percent and 10% of the stored data (10 Tbytes) Network: High speed network connections to CPF. Must be consistent with a flux of 3 days worth of data (32 Mb/s) Cost (2002 price based on LTO) : 355 k + VAT
36 Sommario costi per la parte INFN per il contributo al Ground Segment Centrale (CERN) e IGS relativa al Data Transfer e Master Copy per il periodo HW to AMS central ground segment 277k Personnel (A)SOC,POCC, etc 394k. Total cost 671 k (VAT included) HW (IGSDS) for 200TB storage 428k HW DTF e DTMS (63k) Total cost 491k Grand Total ( ) 1162 k No cost for IGSDS facility (infrastructure and personnel) is included