Scaricare la presentazione
La presentazione è in caricamento. Aspetta per favore
1
Accelerator Disision March 3rd 2015
KLOE-2 data taking: Status and open points Catia Milardi Accelerator Disision March 3rd 2015
2
Peak Luminosity 24 Nov 2014 95 bunches Lpeak [cm-2s-1] 4.53•1032
DANE CW upgrade SIDDHARTA (2009) DANE KLOE (2005) DANE (CW) KLOE (2012) KLOE-2 (2014) Lpeak [cm-2s-1] 4.53•1032 1.50•1032 1.52•1032 1.80•1032 I- [A] 1.52 1.4 0.93 1.11 I+ [A] 1.0 1.2 0.72 0.88 Nbunches 105 111 100 95
3
Hourly integrated Luminosity
24/11/2014 L∫1 hour = pb-1 moderate injection regime L∫day > 11 pb-1 possible Background was compatible with the detector data-taking
4
4/12/2014 Iniezioni rallentate per problemi a:
Switch sistema d’iniezione UFS Linac Spegnimento alcuni CHV short e long Accesso KLOE in sala DAFNE Si osserva una generale lentezza del Linac nell’andare a regime nel funzionamento per e+
5
Best operation day (2004 – 2005)
6
DAFNE performance for KLOE :
nbunches = up to I-total = A I+total = A Lpeak ~ 1.5x1032 cm-2 s-1 L∫day ~ 10 pb-1 (maximum value) L∫KLOE run = 2 fb-1 (May 2004 ÷ Nov 2005) Lpeak Peak and daily integrated luminosity during the KLOE runs. The maximum value of L∫day ~ 10 pb-1 has been obtained in Nov 2005. L∫day
8
Lpeak at DANE 2001 ÷ 2007 Llogged (fb-1) 2001÷2007
Lpeak had a remarkable evolution mainly due to several machine upgrades Experiments took data one at the time, although DAΦNE had been originally conceived as a double Ips collider Luminosity [cm-2 s-1] NEW COLLISION SCHEME KLOE Llogged (fb-1) 2001÷2007 KLOE 3.0 FINUDA 1.2 DEAR 0.2 FINUDA
9
17/11/14 si interviene per ripristinare il funzionamento di SCHES101 – la pompa peristaltica perde olio 18/11/14 24/11/14 riavvio SC complicato 25-26 /11/14 problemi al modulatore D 15/12/14 misure sicurezze 17/12/14 KCKA1001 ingresso KLOE 18/12/14 inefficenze funzionamento RF e- 20/12/14 thyratron mod D 14/2/14 problemi al modulatore B
10
20/12/2014
11
20/12/2014 Setting up the configuration for beta measurements we realized the betatron coupling of the e+ beam has changed wrt 2013
12
Fit
13
Fit
14
These measurements have not been used due to:
Tunes drift during meas CS faults Betatron coupling in the MRp
15
Restarting operation in 2015 some discrepancies have been observed concerning
Collision reference orbit Q2 tuning in MRp Dq > 60% of the expected value Dq > 40% of the expected value with an important variation in Q2 Dq2 seems to work
16
We were able to tune qx+ till almost the end of December
17
10/12/13 23/2/15 |r(PMQFL)| = 0.8625 degree |r(PMQFS)| = 0.8625 degree
BPM disconnected
19
Model is normal mode 1 tilt when a rotation error Dq is added to PMQFL
|Dq| ~ (450 rotation on the knob) which adds to the nominal rotation
20
23/2/2015 Orbit variation after removing the peristaltic pump
21
Programma Betatron coupling correction in MRp Betatron function measurements in both rings aimed at: Testing measurements application Matching Increasing ac Improve phase advance between CWSTPs and IP
22
H e+ 2 beams
23
2 beams V e+
24
H e- 2 beams
25
V e- 2 beams
Presentazioni simili
© 2024 SlidePlayer.it Inc.
All rights reserved.